The April showers arrived in Columbia, SC and have not left yet. Despite the weather, I-77 is progressing. The crews have performed cross slope correction and started the last mainline pull of Surface B in Segment 1. The median construction by Archer Western has been progressing as well.
During the next two months, the concrete will be covered up with Surface B and the ditches paved. Sloan will then proceed to correct the cross slope in Segment 2 northbound and southbound.